2026 Street Project Tree Clearing Schedule
Due to rain on Friday July 31st, the tree clearing operations along Chestnut Street will now take place on Saturday August 1st. R.E. Peterson and their tree sub-contractor will be removing the necessary trees along Chestnut Street then be off site til the middle of next week. Tree clearing along 5th Street will take place next week.
Traffic Impacts: On Saturday, R.E. Peterson will close down the section of Chestnut Street between 5th Street and TH 95 for safety reasons and will re-open Chestnut when clearing has been completed on Saturday. All Chestnut Street residents should use 5th Street to the south in order to enter/exit their property on Saturday August 1st.