2025 Street Improvements Begin May 5
Construction Notice – Phase 1 of 2 Construction Starting
Starting Monday May 5th, 2025, the contractor plans to start street improvements in the Upper Village (map). Affected residents have been notified. This project is a full reconstruction project which will remove all bituminous pavement and place 3.5” of new bituminous pavement.
Anticipated Construction Timeline (subject to change if poor weather conditions arise)
- May 5th: Placing traffic and erosion control.
- May 6th – May 7th: Mill the road and saw cut/remove driveways.
- May 8th – May 15th: Common excavation, place aggregate base, and correct the subgrade of the road tp prepare for base paving.
- May 15th – May 16th: Install all storm sewer improvements.
- May 16th – May 21st: Install concrete curb and gutter.
- May 21st – May 22nd: Tolerance the road.
- May 22nd– May 23rd: Pave the first layer of pavement. Pavement can be driven on about 15-20 minutes after placement. All driveway patching will also be completed at this time. A future notice will be provided prior to placement with additional details.
- May 23rd – May 27th: Topsoil and seed will be placed in disturbed areas.
- May 28th – May 29th: The top layer of pavement will be placed. Pavement can be driven on about 15-20 minutes after placement. A future notice will be provided prior to placement with additional details.
- May 29th – June 3rd: Shouldering of the roadway will take place during this time.