Summer 2026 Road and Construction Projects
2026 Street Project Tree Clearing Schedule
7/31/2026
Due to rain on Friday July 31st, the tree clearing operations along Chestnut Street will now take place on Saturday August 1st. R.E. Peterson and their tree sub-contractor will be removing the necessary trees along Chestnut Street then be off site til the middle of next week. Tree clearing along 5th Street will take place next week.
Traffic Impacts: On Saturday, R.E. Peterson will close down the section of Chestnut Street between 5th Street and TH 95 for safety reasons and will re-open Chestnut when clearing has been completed on Saturday. All Chestnut Street residents should use 5th Street to the south in order to enter/exit their property on Saturday August 1st.
2026 Street Project Delayed
7/27/2026
Marine on St. Croix's 2026 Street Project has been pushed to late August, pending Xcel Energy’s schedule to relocate the poles along Chestnut St.
The City will deliver updated notices to residents with the schedule once the engineer has confirmation from Xcel. Tree clearing will be needed prior to construction start for Xcel to place the poles in the correct location.
Not impacted: The scheduled maintenance chip sealing in the Rose-Wilke neighborhood and Jackson Meadow will continue as planned. Residents should have recieved notices last week.
Summer 2026 Roadwork: What to Expect
4/1/2026
The City of Marine on St. Croix will complete a targeted street improvement project in 2026, with construction expected from late spring through summer.
Full Reconstruction: Portions of Fifth Street and Chestnut Street
- Rebuilding the southern 315 feet of Fifth Street, to a width of 12 feet with new base material
- Rebuilding Chestnut Street from Fifth Street to Minnesota State Highway 95, to a width of 12 feet with new base material
- Resurfacing the Fifth Street trail connection to Chestnut (8 feet wide)
- An additional segment of Chestnut Street with new pavement (westward to the top of the hill), included as an alternate improvement
- A potential decommissioning of the gravel connection between Sixth Street and Pratt Street through the School Forest has been tabled and will be reviewed further.
2026 Maintenance Project (Crack Filling and Seal Coating): Wilke, Rosabelle, Rose, Holmes, Berkey St., and in Jackson Meadow. Jackson Meadow was scheduled for full pavement replacement in 2032. In February, council members and city staff discussed options for addressing poor road conditions, ranging from low cost "band-aid" projects to larger scale paving projects. After weighing the impact of increased roadwork this year on future timelines, they settled on double chip sealing Jackson Trail, Blue Heron, Egret, Kingfisher, Osprey, and Sandpiper lanes this year, and moving full pavement replacement up two years, to 2030.
What residents should expect
Residents near the project areas should expect temporary disruptions during construction, including limited access and increased truck and equipment traffic. As the work schedule solidifies, neighborhood residents will receive notices with dates and details.
Budget
In March, City Council awarded the 2026 Street Improvement Project to R.E. Peterson Inc. for a total of $159,099.50. This includes the base bid and an additional segment of Chestnut Street. The budget for the 2026 Maintenance Project is $130,000; the project will be brought to Council in April to request approval to solicit quotes from contractors.